Comment on The four houses dads belong to.
tim-clark@kbin.social 11 months agoLarge pieces of billet material, lift point added for moving between machines on the first 2 operations. Afterwards the item is light enough to pickup. Roughly 323lbs of material removed in the first 2 operations. Then the items went on to 6 months of machining to complete them. Very expensive one off pieces manufactured during R&D. Final products are low number runs of 2-3 items that take 5 months to manufacture. This was a single piece in a larger piece of equipment that I manufactured. Largest tolerance on the item was 0.0005" with true position at 0.0001". Challenging item to handle and machine
Fuck_u_spez_@sh.itjust.works 11 months ago
What were they parts of?
tim-clark@kbin.social 11 months ago
Wafer manufacturing. High heat application for the unit, part described is the main internal platter